Robinson Drive

The City of Prescott and Capital Improvements, LLC, are working on the second phase of the Robinson Drive Reconstruction Project. The second phase of the project consists of full road removal and replacement of Robinson Drive, from Overstreet Drive to the City limit at the intersection of Canyon Drive East. Additional work includes the installation of new storm drain along Hillcrest Lane, replacement of aged water and sewer lines, drainage improvements, and installation of concrete sidewalks, driveway entrances, and curb and gutter as needed along the project corridor.

The project is scheduled to be complete in summer 2020.

Please be aware of the following impacts: Monday through Friday, May 11-15, from 7 a.m. to 6 p.m. Robinson Drive will be closed to through traffic between Overstreet Drive and Newport Drive.

• Crews will continue excavating the roadway and preparing the subgrade and base course along Robinson Drive, between Overstreet Drive and Newport Drive, throughout the week.

• The installation of new concrete sidewalk and curb and gutter along Robinson Drive, between Overstreet Drive and Newport Drive, will continue throughout the week. In addition to this work, crews will continue constructing new retaining walls along the project corridor.

Corsair Avenue

photo

A map of the Corsair Avenue work. (City of Prescott/Courtesy)

The City of Prescott and Fann Contracting, Inc., are working on a roadway extension project. The project consists of constructing a new roadway connection between the existing southern terminus of Corsair Avenue to an intersection with Wilkinson Drive. The intersection of Wilkinson Drive and Corsair Avenue will feature a single lane roundabout to accommodate for peak traffic flows. The new extension of Corsair Avenue will include two paved travel lanes complete with a paved center median and new curb and gutter. In addition to this work, the project includes both drainage and utility improvements.

The project is scheduled to be complete in fall 2020.

Please be aware of the following impacts: Monday through Friday, May 11-15, from 7 a.m. to 6 p.m.

• Crews will continue performing grading operations along Corsair Avenue, just south of Avenger Road, in preparation of new roadway construction and utility installation.

Cliff Rose Water Main

The City of Prescott and Capital Improvements, LLC, are working on a water main replacement project. The project includes installation of new water main and services along Boardwalk Avenue, from Rosser Street to Marvin Gardens Lane, and along Marvin Gardens Lane, from Boardwalk Avenue to Oriental Avenue (cul-de-sac included). Additional work includes asphalt pavement patching and the removal and replacement of concrete curb and gutter, as needed, along the project corridor.

The project is scheduled to be complete in Fall 2020.

Please be aware of the following impacts: Monday through Friday, May 11-15, from 7 a.m. to 6 p.m. Marvin Gardens Lane will be closed to through traffic while this work is underway.

• Crews will continue installing a temporary water flyline along Marvin Gardens Lane, from Oriental Avenue to the Marvin Gardens cul-de-sac. Once the flyline is installed, crews will begin installing new water main along Marvin Gardens Lane.

Hope Street

The City of Prescott and Asphalt Paving & Supply, Inc., are working on a utility improvements project, which consists of replacing approximately 1,150 linear feet of water main, performing a sewer main repair, and installing drainage improvements, asphalt pavement, and curb and valley gutters along Hope Street and Warne Street, as highlighted on the map below.

The project is scheduled for completion in spring 2020.

Please be aware of the following impacts: Monday through Friday, May 11-15, from 7 a.m. to 6 p.m.

• Crews have finished removing the old water main within Hope Street and Warne Street. With this work complete, crews will continue excavating the roadway and preparing the subgrade in advance of asphalt paving operations.

Summit, McCormick, Beach, and Goodwin

The City of Prescott and Fann Contracting, Inc., are currently working on a pavement and utility upgrade project along Summit Avenue, Beach Avenue, South McCormick Street, and West Goodwin Street. The project consists of the replacement of various water lines, sewer lines, and storm drain pipe. Additional improvements include the installation of new catch basins, driveway entrances, sidewalk, curb and gutter, and asphalt reconstruction. The project is scheduled to be complete by summer 2020.

Please be aware of the following impacts: Monday through Friday, May 11-15, from 7 a.m. to 7 p.m.

• Crews will be performing grading operations and preparing the subgrade and base course in advance of asphalt paving operations along South Summit Avenue, from West Goodwin Street to West Gurley Street.

• The installation of new water services along South Summit Avenue, from West Goodwin Street to West Gurley Street, and West Goodwin Street, from South McCormick Street to South Summit Avenue, is now complete. Additionally, crews have completed commissioning the newly installed water main along West Goodwin Street. With this work finished, crews will be removing the old water line along West Goodwin Street, from South McCormick Street to South Summit Avenue, throughout the week.

• Crews will be constructing catch basins and installing new storm drain along South McCormick Street, between Beach Avenue and West Goodwin Street, throughout the week.

• Crews will be preparing to install concrete sidewalks, driveway entrances, and curb and gutter along South McCormick Street, between West Gurley Street and West Goodwin Street, throughout the week.

To minimize conflicts with construction equipment, and expedite completion of the projects, the city asks that you avoid on-street parking while construction is underway. Personnel will work with businesses and residents to maintain driveway access throughout the work zones.

Call 928-237-3114 to speak to a project team member with any questions or concerns. Note that in the event of inclement weather the work schedule may be altered or suspended without notice.